SNET Hyperon integration

Project Status

scheduled, waiting for external input

Buffer Status

unlocked

Last Updated

2024-11-20 23:16

Technical Owner

TBD

Business Owner

TBD

Milestone Goal and Deliverables

SNET Hyperon integration goal

Each deliverable is listed along with the required proof of completion.

Current Gantt Chart

Manually updated weekly by the Project Manager and imported from A-Dato Lynx software, which does the automatic resource levelling based on the milestone issues of the GitLab Kanban board.

Current Gantt Chart

Current Fever Chart

Manually updated weekly by the Project Manager and imported from A-Dato Lynx software, which does the automatic resource levelling based on the milestone issues of the GitLab Kanban board.

Current Fever Chart

Work Packages Technical Dependencies

Work Package dependency graph

Each item on the above graph is clickable and points to the technical dependencies graph of each work package -- reflecting current composition and status of work package.

Work Packages Status

Work Packages

Each work package is assigned a collaboration group of developers who work together for closing issues associated with the package. Each work package contains a scope buffer, which allows to account of uncertainty of work package delivery time, in case new issues are identified and added during work.

Last updated