Work Packages

Work Package Data / Updated 2025-06-05 23:08

Finished 0 Work Packages out of 9

Remaining Work Packages Details are as follows:

Critical
Work Package
Owner
Remaining Days
Remaining Issues

No Assignee

0

1 / 3

Pravar Joshi

2

1 / 7

No Assignee

2

1 / 4

No Assignee

2

1 / 6

No Assignee

10

2 / 10

No Assignee

2

1 / 4

No Assignee

2

2 / 4

No Assignee

2

1 / 4

Pravar Joshi

0

1 / 2


0 Days Remaining - 1 / 3 issues Remains

In Backlog
In Development
In Review
Done

2

0

0

1

Owner : No Assignee

Development Members :

Dependant on:


2 Days Remaining - 1 / 7 issues Remains

In Backlog
In Development
In Review
Done

6

0

0

1

Owner : Pravar Joshi

Development Members : Pravar Joshi


2 Days Remaining - 1 / 4 issues Remains

In Backlog
In Development
In Review
Done

3

0

0

1

Owner : No Assignee

Development Members :

Dependant on:


2 Days Remaining - 1 / 6 issues Remains

In Backlog
In Development
In Review
Done

5

0

0

1

Owner : No Assignee

Development Members : Pravar Joshi

Dependant on:


10 Days Remaining - 2 / 10 issues Remains

In Backlog
In Development
In Review
Done

8

0

0

2

Owner : No Assignee

Development Members : Safi Ullah


2 Days Remaining - 1 / 4 issues Remains

In Backlog
In Development
In Review
Done

3

0

0

1

Owner : No Assignee

Development Members :

Dependant on:


2 Days Remaining - 2 / 4 issues Remains

In Backlog
In Development
In Review
Done

2

0

0

2

Owner : No Assignee

Development Members :


2 Days Remaining - 1 / 4 issues Remains

In Backlog
In Development
In Review
Done

3

0

0

1

Owner : No Assignee

Development Members :


0 Days Remaining - 1 / 2 issues Remains

In Backlog
In Development
In Review
Done

1

0

0

1

Owner : Pravar Joshi

Development Members :

Dependant on:


Last updated