Project Status
notScheduled
Buffer Status
unlocked
Last Updated
2025-01-20 23:08
Technical Owner
TBD
Business Owner
TBD
Machine Learning / AI / LLM platforms integration goal
Each deliverable is listed along with the required proof of completion.
Manually updated weekly by the Project Manager and imported from A-Dato Lynx software, which does the automatic resource levelling based on the milestone issues of the GitLab Kanban board.
Manually updated weekly by the Project Manager and imported from A-Dato Lynx software, which does the automatic resource levelling based on the milestone issues of the GitLab Kanban board.
Each item on the above graph is clickable and points to the technical dependencies graph of each work package -- reflecting current composition and status of work package.
Each work package is assigned a collaboration group of developers who work together for closing issues associated with the package. Each work package contains a scope buffer, which allows to account of uncertainty of work package delivery time, in case new issues are identified and added during work.
Work Package Data / Updated 2025-01-20 23:08
Finished 0 Work Packages out of 2
Remaining Work Packages Details are as follows:
Avimanyu Bandyopadhyay
38
1 / 11
Avimanyu Bandyopadhyay
16
8 / 15
38 Days Remaining - 1 / 11 issues Remains
10
0
0
1
Owner : Avimanyu Bandyopadhyay
Development Members : Avimanyu Bandyopadhyay
16 Days Remaining - 8 / 15 issues Remains
7
0
0
8
Owner : Avimanyu Bandyopadhyay
Development Members : Avimanyu Bandyopadhyay - Dagim Sisay - Abhishek Shukla - Pravar Joshi